Materials cost variance scenario: Multiple DMs
Scenario 2: Multiple DMs
ChocoDelight Cookies produces gourmet chocolate chip cookies. The production process uses two types of direct materials: premium chocolate chips (Material A) and organic flour (Material B). The company’s production standards and actual results for a recent batch are outlined below.
To produce 1,000 cookies, the following usage and cost standards apply:
- Material A: 5 kilograms per 1,000 cookies at $10 per kilogram
- Material B: 8 kilograms per 1,000 cookies at $5 per kilogram
Actual results for the recent batch were 1,500 cookies were produced:
- Material A: 6 kilograms at $12 per kilogram
- Material B: 15 kilograms at $6 per kilogram
Calculate the direct materials variances:
- Materials price variance
- Materials usage variance
- Materials mix variance
- Materials yield variance
- Materials cost variance
If you would like to check the over-all solution, you can skip to the Scenario summary section at the end of this page.
The 1,000-cookie figure is just the basis for the standard rates; all quantity variances use the standard quantity allowed for actual output of 1,500 cookies.
Scenario 2.1. Materials price variance
We need to get the total of the price variances of each direct material, using the factored form .
The variance is unfavorable because the actual price per unit of Material A ($12) is higher than standard price ($10). of Material A is already available at 6 kilograms and does not need further computations.
The variance is unfavorable because the actual price per unit of Material B ($6) is higher than standard price ($5). of Material B is already available at 15 kilograms and does not need further computations.
Scenario 2.2. Materials usage variance
The to be used here is not the one in the master budget but the standard quantity that would have been used by the actual production of 1,500 cookies. The following are the for both Material A and B:
After the is determined, we need to get the total of the usage variances of each direct material, using the factored form .
The variance is favorable because the actual Material A used by production (6 kg) is lower than standard (7.5 kg).
The variance is unfavorable because the actual Material B used by production (15 kg) is higher than standard (12 kg).
The favorable usage variance of Material A was offset by the unfavorable variance of Material B. This total usage variance can be verified by the computation of the materials mix and materials yield variances, shown next.
Scenario 2.3. Materials mix variance
The materials mix variance measures the cost effect of blending the materials in different proportions than the standard mix, holding the actual total quantity of materials used constant.
Once all the above are determined, we can calculate the variances separately for each direct material.
The favorable variance of $20.8 indicates that less Material A was used than expected in the standard mix, resulting in cost savings.
The unfavorable variance of $10.4 shows that more Material B was used than expected in the standard mix, leading to higher costs.
Scenario 2.4. Materials yield variance
The materials yield variance measures the cost effect of using a different total quantity of materials than the standard allows for actual output, holding the mix at the standard proportions.
The unfavorable variance of $5.8 indicates that the overall production process required more input than expected, and Material A’s portion of the excess input increased costs.
The unfavorable variance of $4.6 reflects that additional input was used in production, with Material B’s share contributing to higher costs.
We can also verify the Materials Usage Variance computed in 2.2:
Here’s what these totals mean: the mix shifted toward the cheaper flour (Material B, standard $5 per kilogram) and away from the pricier chocolate chips (Material A, standard $10 per kilogram), producing the $10.4 favorable mix variance. At the same time, total materials input (21 kg) came in above the 19.5 kg standard allowed for 1,500 cookies, producing the $10.4 unfavorable yield variance - the two exactly offset, which is why the usage variance nets to zero. That offset is worth noticing: it means the $27 unfavorable materials cost variance is driven entirely by price, not quantity. A likely explanation is a recipe or process deviation (using relatively more flour and less chocolate than the standard formula calls for) combined with higher purchase prices for both materials. Corrective actions worth investigating include renegotiating supplier prices and reinforcing adherence to the standard recipe on the production line. (These totals are rounded from unrounded mix percentages; the exact mix and yield variances are each about $10.38.)
Scenario 2.5. Direct material cost variance
The material cost variance can be computed by adding up the price and the usage variances:
Alternatively, we can also use the cost variances per type of DM and we should get the same answer:
Scenario summary
The following illustration shows the summary of the variances for Scenario 2:
