Overview of materials cost variance formula
Material cost variance is the total difference between the standard cost of materials and the actual cost incurred for materials.
The general formula for this is expressed below:
A positive result is favorable (actual cost below standard); a negative result is unfavorable.
Example: Total materials cost variance
A company budgeted 9,000 units but produced 10,000, with a standard of 2 kg/unit at $3/kg. Actual usage was 20,500 kg at $2.90/kg.
Standard quantity (flexed to actual output): kg.
Standard cost $60,000 − actual cost $59,450 = $550 favorable.
Answer: $550 favorable; the price and usage variance chapters split this further.
The materials cost variance is broken down into different variances in order to isolate the sources of the deviations from the standard costs and usage. The variance is coming mainly from two sources:
- differences between standard price versus actual price paid for materials (materials price variance); and
- the differences between the standard consumption versus the actual consumption (materials usage variance). The usage variance can be further broken down when there are more than one direct materials used in production as this also impacts total costs.
When more than one material is used, this split is called the mix variance and the yield variance (covered in the next chapter).
Overview of variance formula
When the quantity of materials used in production matches the quantity purchased, the total of all calculated variances should equal the overall materials cost variance. This provides a useful way to verify the accuracy of your calculations by comparing the sum of the individual variances to the total materials cost variance.
Price variance plus usage variance equals the total variance; mix plus yield equals the usage variance.

