Labor cost variance scenario: Multiple DLs
Scenario 2: Multiple types of direct labor
ChocoDelight Cookies continues its operations with a focus on producing gourmet chocolate chip cookies. To assess production efficiency and cost management, the company now wants to analyze its direct labor performance. The production process involves two types of labor: skilled bakers (Labor A) and assistant bakers (Labor B). Below are the standards and actual data for a recent production batch.
To produce 1,000 cookies, the following usage and cost standards apply:
- Labor A: 6 hours per 1,000 cookies at $20 per hour
- Labor B: 4 hours per 1,000 cookies at $10 per hour
Actual results for the recent batch were 1,500 cookies were produced:
- Labor A: 8 hours at $22 per hour
- Labor B: 8 hours at $12 per hour
Calculate the direct labor variances:
- Labor rate variance
- Labor efficiency variance
- Labor mix variance
- Labor yield variance
- Labor cost variance
If you would like to check the over-all solution, you can skip to the Scenario summary section at the end of this page.
All formulas on this page are written as standard minus actual. A positive result is favorable (it raises operating income), and a negative result is unfavorable; we show the dollar amount with an F or U label.
Scenario 2.1. Labor rate variance
We need to get the total of the rate variances of each type of direct labor.
The unfavorable variance of $16 indicates that skilled bakers were paid $2 more per hour than the standard rate, increasing labor costs. Actual Hours (AH) of Labor A is already available at 8 hours and does not need further computations.
The unfavorable variance of $16 indicates that assistant bakers were also paid $2 more per hour than the standard rate.
The total unfavorable variance of $32 reflects higher-than-expected hourly wages for both skilled and assistant bakers, leading to increased overall labor costs.
Scenario 2.2. Labor efficiency variance
The to be used here is not the one in the master budget but the standard hours that would have been used by the actual production of 1,500 cookies. The following are the SH for both Labor A and B:
We then need to get the total of the efficiency variances of each type of direct labor.
The favorable variance of $20 shows that skilled bakers worked fewer hours than expected, saving costs.
The unfavorable variance of $20 indicates that assistant bakers worked more hours than expected, increasing costs.
A $0 total efficiency variance does not mean hours were on target. Total actual hours (16) exceeded standard hours (15), but shifting toward cheaper assistant bakers saved exactly as much as the extra hour cost. The mix and yield variances below separate these two effects.
This total efficiency variance can be verified by the computation of the labor mix and labor yield variances which will be shown below.
Scenario 2.3. Labor mix variance
Once all the above are determined, we can continue calculating the variances for each type of direct labor.
The favorable variance of $32 indicates that fewer skilled baker hours were used compared to the standard mix, reducing labor costs for this category.
The unfavorable variance of $16 reflects that more assistant baker hours were used than expected in the standard mix, increasing overall costs.
Scenario 2.4. Labor yield variance
The unfavorable variance of $12 indicates that the overall labor process required more hours than expected, increasing costs for skilled bakers.
The unfavorable variance of $4 reflects that excess total hours also raised costs for assistant bakers.
The $16 unfavorable variance highlights inefficiencies in labor utilization, leading to higher-than-expected costs.
We can verify the labor efficiency variance below by adding the mix and yield variances:
Scenario 2.5. Direct labor cost variance
The labor cost variance can be computed by adding up the rate and the efficiency variances:
Alternatively:
Together, these variances point to two separate causes. The $16 F mix variance came from substituting assistant-baker hours for skilled-baker hours, and that same substitution is the likely cause of the extra hour behind the $16 U yield variance - the cheaper labor mix took longer to finish the batch. The $32 U rate variance is a separate issue: both labor types were paid above their standard rates, which calls for a review of wage rates or overtime pay rather than labor mix. Management should judge the staffing decision by its net effect on total cost, not by the favorable mix variance alone.
Scenario summary
The following table shows the summary of the labor variances for Scenario 2:
This table summarizes the labor cost variances for Scenario 2: a total labor rate variance of $32 unfavorable, a total labor efficiency variance of $0 made up of a $16 favorable mix variance and a $16 unfavorable yield variance, and a total labor cost variance of $32 unfavorable.
| Variance | Labor A | Labor B | Total |
|---|---|---|---|
| Rate variance | $16 U | $16 U | $32 U |
| Mix variance | $32 F | $16 U | $16 F |
| Yield variance | $12 U | $4 U | $16 U |
| Efficiency variance (mix + yield) | - | - | $0 |
| Cost variance | $4 F | $36 U | $32 U |
The illustration below is carried over from the materials-variance scenario and does not depict this labor scenario; use the table above for the labor figures.
