FOH cost variance scenario
FOH cost variance scenario
ChocoDelight Cookies allocates fixed overhead (FOH) costs related to facility maintenance for its production facility. These costs include utilities, equipment upkeep, and general building maintenance. Management wants to evaluate how effectively fixed overhead costs are being utilized and absorbed into production.
Standard FOH data
In the master budget, ChocoDelight Cookies allocated a total fixed overhead cost of $400 for the production of 1,000 cookies. The standard production process requires 10 direct labor hours per 1,000 cookies.
Actual FOH data
The actual production resulted in a batch of 1,500 cookies. The company incurred actual fixed overhead costs of $650. The production process utilized 16 actual direct labor hours for this level of production.
Calculate the FOH variances:
- VOH spending variance
- Production volume variance
- FOH capacity variance
- FOH efficiency variance
- FOH cost variance
Scenario 1.1. FOH spending variance
The unfavorable variance of $250 indicates that the company incurred higher fixed overhead costs than budgeted for the production facility. All the inputs required for the computation are readily available in the problem. This is typical for the FOH spending variance.
Note that unlike other variances discussed previously, the FOH spending variance actually uses the amount in the Master Budget rather than calculating the standard based on actual production.
Scenario 1.2. Production volume variance
The can be computed solely from unit-level FOH allocation (ignoring the direct labor hour allocations which will be relevant only if we want to split the volume variance into FOH capacity and FOH efficiency variances).
The FOH absorption rate would be .
At production of 1,500 cookies, the absorbed FOH is .
The favorable variance of $200 indicates that the company produced 500 more cookies than planned, leading to better absorption of fixed overhead costs.
As mentioned previously, we can compute the FOH capacity and FOH efficiency variances when the cost driver of the FOH is provided in the problem. This is shown in the next section.
Scenario 1.3. FOH capacity variance
Where:
- is the standard FOH rate. This could be calculated using the master budget.
- are the budgeted hours expected to be produced in the master budget.
- are the actual hours incurred by production.
The should be computed per Direct Labor hour (cost driver) and not per unit produced (i.e. cookie).
In this case, the SFR should be: .
The favorable variance of $240 indicates that more direct labor hours were worked than the standard hours allocated for the budgeted production, leading to improved utilization of fixed overhead resources.
Scenario 1.4. FOH efficiency variance
Where:
- is the standard FOH rate. This could be calculated using the master budget.
- are the standard hours allowed for the actual units produced.
- are the actual hours incurred by production.
The portion of the formula refers to the .
The unfavorable variance of $40 reflects that the actual labor hours exceeded the standard hours required for the actual production volume, resulting in less efficient use of fixed overhead resources.
Scenario 1.5. FOH cost variance
Alternatively:
The unfavorable variance of $50 indicates that the incurred ($650) exceeded the by production ($600). Although the company produced more than the budgeted volume, resulting in favorable absorption of overhead costs, the higher actual fixed overhead spending ultimately led to an overall unfavorable variance. This highlights the need to control fixed overhead spending to prevent similar variances in the future.